Sourcing GuideJune 1, 2026

From Sample to Bulk: The Apparel Production Timeline Explained

How long does it really take to manufacture custom apparel? A week-by-week breakdown from sample approval to delivery.


One of the most common questions from new apparel buyers is: "How long will this take?" Here is a realistic timeline for custom garment production.


The Complete Timeline


| Phase | Duration | What Happens |

|-------|----------|--------------|

| Sample development | 5-10 business days | Fabric sourcing, proto sample, fit sample |

| Sample approval | 1-3 business days | Customer reviews and approves |

| Fabric procurement | 3-7 business days | Order fabric, await delivery to factory |

| Production cutting | 2-3 business days | Fabric laid, cut by pattern |

| Sewing & assembly | 5-10 business days | Garments sewn, trimmed, inspected |

| Decoration (if any) | 3-5 business days | Screen printing, embroidery, or DTG |

| Final QC | 1-2 business days | AQL inspection, measurement check |

| Packing | 1-2 business days | Fold, polybag, carton, label |

| Shipping | Varies | Sea: 15-25 days. Air: 3-7 days |


**Total production (without shipping):** 15-35 business days


Sample Types Explained


- **Proto sample** β€” First physical version. Checks silhouette, sizing, construction

- **Fabric swatch** β€” Small piece of the actual fabric for color and hand-feel approval

- **PP sample (Pre-Production)** β€” Made from the actual production fabric using the final patterns

- **Shipment sample** β€” Pulled from the production run before shipping


What Accelerates Production


- **Approved tech pack** β€” Detailed spec sheets reduce back-and-forth

- **Standard fabric** β€” In-stock fabrics ship immediately; custom mill runs take 2-3 weeks extra

- **Simplified trim** β€” Stock thread colors, standard zippers, and available labels

- **Seasonal timing** β€” August-October (pre-holiday) is peak season; Q1 and mid-summer are faster


What Delays Production


- Multiple sample revisions (each adds 5-10 days)

- Custom fabric orders

- Holiday closures (Chinese New Year: factory closed 2-4 weeks)

- Mid-production design changes


BOAZ Production Timeline


For standard blank t-shirt orders (50-500 pieces), we ship within **5-10 business days** from order confirmation. Custom cut-and-sew projects typically complete in **20-25 business days** from sample approval. We provide a detailed timeline with your quote.